Risk Register
7 open risks across the lifecycle · ranked by production impact
Open risks
| ID | Risk | Stage | Severity | Time to impact |
|---|---|---|---|---|
| RSK-071 | Line 3 interruption — SHP-4821 delay | Move | Critical | 19 h |
| RSK-068 | PCK-003 failure within 72h | Operate | Critical | 72 h |
| RSK-064 | Utilities 9 days behind schedule | Build | High | 143 d |
| RSK-061 | Atlas Pumps late delivery | Build | High | 6 d |
| RSK-057 | Seal quality drift on Family A | Operate | High | — |
| RSK-052 | Automation commissioning blockers (3) | Build | High | — |
| RSK-049 | SHP-4882 electronics +2h | Move | Medium | 2 h |